THE OWNERS DUTIES IN
CONSTRUCTION
The owner's failure to understand and perform his
duties can seriously affect a project.
Two years ago, a 26-story condominium was completed in
South Florida. At the initial contract signing, the owner stated that the next
time he wanted to see the contractor was when he received the keys to the
building. The project was completed six months late. The contractor then filed
a claim for an extension of time and the associated general conditions costs.
The claim was based on the owner's failure to perform his duties as stated in
the contract, often causing project delays. In fact, the owner had not
appointed an authorized representative to oversee the project and had reserved
all authority for project decisions to himself. To make matters worse, the
owner would sometimes leave the country for 6 weeks at a time.
Upon receipt of the contractor's claim, the owner
filed a counter claim for $1 million in liquidated damages. A distinguished
panel of three arbitrators decided the matter. They not only denied the owner's
claim, but they awarded the contractor 6 months of general conditions and home
office overhead, cost of acceleration, interest, and lost profits totaling
almost $2 million - all directly resulting from the owner's failure to perform
his duties during construction.
A favorite analogy that is often used to describe
the parties involved in a construction project is a "ladder." The two
legs represent the owner and the contractor. Using this analogy, it is easy to
visualize what happens when one of the legs fails to support its share of the
weight on the ladder. It can be embarrassing and painful.
Our society has created institutions to educate,
certify, license, and regulate contractors. However, no license or
certification is required to be an owner. For this reason, the owner's leg of
the ladder is the one to be the most concerned about. The owner is responsible,
by law, for certain duties to the contractor and the public. To the designer,
the owner must furnish the background information and services needed for the
designer's work and must reasonably compensate the designer. To the contractor,
the owner must provide sufficient information and services in a continuous and
timely manner, to enable the contractor to perform according to the
construction contract. To the public, the owner must provide a building that is
safe for its intended use, while complying with codes and zoning laws.
The following is a summary of the many tasks that
must be performed by the owner during the successful development of any
building project.
PRE-DESIGN PHASE
Development of the program - This is the project's cornerstone. The
owner must clearly state the project objectives, develop a master schedule, and
prepare a budget. Many things must be considered including space requirements,
adjacency of functions, expendability, constraints, and equipment.
Selection
of the site - A favorite saying in real estate is "location, location,
location". There are other considerations in selecting a site such as
constructability, zoning, access, environmental contamination and of course,
cost.
Site
analysis - It is the owner's responsibility to have the property surveyed to
identify set backs, easements, boundaries, and elevations. In addition the
owner must have the site tested and certified for contaminates. Geotechnical
borings are required to determine the structural and drainage capabilities of
the soil.
Selection
of consultants - The owner needs not only a design/build general contractor,
but also consultants for accounting, legal and insurance requirements for the
project. Engineers are usually selected by, and work for, the designer. Once
these consultants are selected, the owner must negotiate contracts with each of
them.
Appointment of an owner's representative for the project Although the
designer typically has broad authority during the project, the owner must
appoint someone as his general agent to represent him in all matters relative
to the project, including oversight of the designer.
DESIGN PHASE
Design approval
- As the designer proceeds with the plans and specifications for the project,
the owner must review and approve them at different stages of completion. At
least four formal approvals are typical.
Budget
approval - With the last formal review of the plans and specifications, the
owner needs to have a professional cost estimate prepared to ascertain whether
the proposed design will be within the original budget.
Development of an FF&E plan - For the building to be functional it
will have to have furniture, fixtures, and equipment. This includes desks,
chairs, artwork, process equipment, and computers. An FF&E plan must
include selection, space coordination, pricing, procurement, storage, and
installation.
Making
decisions on design options - The designer will provide design options to the
owner for final determination. This includes selecting colors and textures, as
well as making tough value engineering decisions.
Creation
of a project communications system - Many individuals are involved in every
project. Timely communications among the parties are necessary for a successful
project.
Development of a project financing and insurance program - The owner
must be able to pay for the work and make sure the proper insurance coverages
are in place before construction begins.
Establishment of allowances - For items of work that are not clearly
defined at the start of the work, the owner must establish cost allowances to
be included in the construction contract.
CONSTRUCTION PHASE
Execution
of the construction contract - Before work can begin, the contract with the
contractor must be executed. In addition, the contractor should provide his
bonds and evidence of insurance before mobilizing on the site. (If required)
Approval of the construction schedule - The
contractor should provide a comprehensive construction schedule soon after
execution of the contract. It is the owner's responsibility to not only review
and approve the schedule, but also to monitor the schedule during construction
and to require periodic updates from the contractor.
Reconciliation of allowances - In order not to impede the progress of
the work, the owner must finalize the scope of the work for each cost allowance
and provide a change order to the contractor reconciling each allowance as
quickly as possible.
Inspection
and testing of the work - The designer and contractor have limited
responsibility to inspect and approve the work as its being completed. It is
the owner's responsibility to continuously and comprehensively inspect the work
to insure compliance with the contract documents.
Project
safety - The owner is responsible to insure that the contractor has a safety
plan in place at the site.
Approval of
changes - Designers do not warrant that their plans will be perfect. Conflicts
in the plans may arise which will require change orders to the construction
contract. It is the owner's responsibility to provide these change orders and
to fund the cost of the changes. In addition, the owner's program may change
during the construction, which may affect the design. Prompt preparation and
execution of change orders is necessary to keep the project on schedule.
Approval
of colors and products - The contractor will ask the owner to make final
decisions on colors, materials, and other design matters. Approval of these
colors is very crucial to the outcome of the scheduled end date.
Monitoring
subcontractors' and suppliers' payments In order to protect himself and to
protect his rights under the contractor's bonds, the owner must have a program
that enables him to insure that all subcontractors and suppliers are being paid
in a timely manner by the contractor. (Lien waivers)
Resolution of disputes - Differences of opinion will occur from time to
time on every project. It is the owner's responsibility, and to his benefit, to
resolve them quickly.
Adjustment and administration of property insurance claims - In the
event that the project suffers a casualty loss covered by property insurance,
sometimes referred to as "builder's risk insurance", then it is the
owner's responsibility to promptly administer the adjustment of the claim on
behalf of all the covered parties.
Procurement and installation of FF&E - As stated above, this
function must be administered in a timely manner by the owner, if the final
product is to be functional.
Development of an operations and maintenance staff - Upon substantial
completion of the project, the contractor will turn over to the owner the
responsibility for operating and maintaining the facility. The owner needs to
have a staff in place prior to this event.
Coordination of separate contractors - Sometimes the owner decides to
have more than one prime contractor involved in the project. Specialty
contractors are a good example, such as kitchen equipment contractors or data
processing contractors. It is the owner's responsibility - not the contractor's
- to coordinate the various prime contractors on the site. If these contractors
are part of main contract the general contractor will coordinate these
contractors.
Conduct
project meetings - A system of periodic management meetings needs to be
established at both the staff and executive levels. Agendas and minutes need to
be prepared by the owner for these meetings, if they are to have value.
Acceptance
of the work. Once the work is completed, only the owner has the authority to
accept it from the contractor.
Establishment of a warranty program. Since the owner is the beneficiary
of the construction and manufacturers' warranties, the owner must set up a
program to manage and administer these warranties.
POST CONSTRUCTION PHASE
Creation
of "as built' records - The availability of a complete "as
built" set of plans will be invaluable in the future for remodeling,
additions, and repairs. They are also beneficial if the building is sold to
another owner.
Administration of the warranty program - Someone needs to oversee the
warranty program after the building is finished.
Determination that everyone was paid - In order to keep the property
free of liens after completion of the construction phase, the owner must insure
himself that the contractor has been paid in full and has provided final lien
releases.
Facility
operations and maintenance - In order to protect the investment made in the
building, the owner must have a comprehensive operations and maintenance
program.
It is plain from the above list that the owner has a
significant number of varied responsibilities in the development of a building
construction program. He cannot simply hire a designer and a contractor and
walk away expecting them to take care of the project on their own. The owner's
failure to discharge his construction responsibilities can have major
consequences.
In conclusion, the performance of the owner during a
construction project has as much affect on the success of the project as the
performance of the designer and contractor. Unfortunately, many owners do not
understand their responsibilities and suffer the ultimate consequences. Owners
who properly address their construction duties will enjoy the benefits of a
successful project upon completion.
This article was copied from Southeast Real
Estate Business
The article was written by John A. Jones, P. E.
John A. Jones is President and CEO of Dart
Engineering, LLC.